Well, it happened-- vids of the pour. More notes later. These show cement mix being poured into ICF, also note guy working rebar up and down to avoid air pockets forming.
Showing posts with label ICF. Show all posts
Showing posts with label ICF. Show all posts
Tuesday, December 13, 2011
Sunday, December 11, 2011
Sunday, November 20, 2011
Exterior walls almost done
Exterior walls are basically done. Window locations finalized and will be cut out shortly.
Once the carport storage room is set, it'll be time for the pour. First, there'll be rebar placed vertically and horizontally through the entire grid. Then, a nice wet concrete mix will be poured through all the cavities.
View of the master:
View of the kitchen:
View of the master and master bath:
Another shot of the master:
Once the carport storage room is set, it'll be time for the pour. First, there'll be rebar placed vertically and horizontally through the entire grid. Then, a nice wet concrete mix will be poured through all the cavities.
View of the master:
View of the master and master bath:
Another shot of the master:
Wednesday, November 16, 2011
Tuesday, November 15, 2011
ICF block details
The blocks are about 7 foot long, 15 inches tall, 10 inches wide.
Heavier than you'd expect-- you see the foam, but the particles are held together by cement.
I believe these are called "screen grid" blocks, in that the channels form a horizontal-vertical grid for concrete (as opposed to flat "ice cream sandwich" or almost-flat "waffle" type panels with an open void in between our and inner sides of the blocks.
The cylindrical channels running through and across the blocks are about 4 inches in diameter.
Due to the 15 inch height, this also means that the center-to-center spacing of the channels is 15".
Heavier than you'd expect-- you see the foam, but the particles are held together by cement.
I believe these are called "screen grid" blocks, in that the channels form a horizontal-vertical grid for concrete (as opposed to flat "ice cream sandwich" or almost-flat "waffle" type panels with an open void in between our and inner sides of the blocks.
The cylindrical channels running through and across the blocks are about 4 inches in diameter.
Due to the 15 inch height, this also means that the center-to-center spacing of the channels is 15".
Saturday, October 15, 2011
slabslabslabslab
I guess this is the part where you realize it's really going to be a house.
Slab has been poured:
The slab shows that the house is divided lengthwise into thirds: one third is the master, one third is kid's rooms and bathroom and laundry, and middle third is open kitchen and living area. Plus middle third continues to include an outdoor living room (in the above pic, that's poking out towards the camera).
There's also a little outdoor kitchenette area, aka, couple of feet of slab for a grill, right off the kitchen (top right corner in this pic):
One of the more notable ICF-specific elements are the pieces of rebar poking out along the exterior walls. These are used to mount the ICF blocks. Walls are about a foot thick when all is said and done (I think 10" for the blocks themselves, plus an inch or two for exterior stucco and interior plaster):
And all spare concrete (along with unused 2x4 scraps) is used to make some large pavers for the walkway between house and carport:
Slab has been poured:
The slab shows that the house is divided lengthwise into thirds: one third is the master, one third is kid's rooms and bathroom and laundry, and middle third is open kitchen and living area. Plus middle third continues to include an outdoor living room (in the above pic, that's poking out towards the camera).
There's also a little outdoor kitchenette area, aka, couple of feet of slab for a grill, right off the kitchen (top right corner in this pic):
One of the more notable ICF-specific elements are the pieces of rebar poking out along the exterior walls. These are used to mount the ICF blocks. Walls are about a foot thick when all is said and done (I think 10" for the blocks themselves, plus an inch or two for exterior stucco and interior plaster):
And all spare concrete (along with unused 2x4 scraps) is used to make some large pavers for the walkway between house and carport:
A few more pics just to make it clear what things look like. For me, this is the first day when the actual size of the house and rooms is perceptually clear. Even with the slab molds in place, it was hard to envision.